Gillaroo
Home
Plans and crew
Past crew
The Build
2003
Design
Model
Workshop & Table
Infusion
2004
Assembling hulls
2005
Hull Bulkheads
Bridgedeck Floor
Superstructure
2006
Completing Shell
Interior
2007
Painting
Interior
Exterior
2008
Completion
Time and Materials
Links and Suppliers
Launch
First time
Relaunch
Equipment issues
Hardware
Modifications

Cruising
2008
Ireland
N.Spain
Portugal & Tarifa
Canaries
2009
St Vincent & Grenadines
Trinidad & Tobago
Dutch Antilles
Panama 1 P 2 P 3 P 4 P 5
Galapagos 1 G 2
Marquesas 1 M 2
Tuomotos
Societies 1 S 2
Cooks 1 C 2
Niue
Tonga 1 T 2
2010
New Zealand NZ2 NZ3 NZ4
Fiji 1  Fiji 2  Fiji 3
Vanuatu 1
wpa9f08a11.png
Time and Materials - Expenditure  and estimates.

All values in Sterling. Some of the ‘Estimate’ values were revised 18 months into the project, my original materials estimate was £101,000. They exclude rental of the site and various the personal overheads we incurred. The working hours are for actual construction work only up to the time of launch and don’t include research, design, purchasing, project managing, ....
Profession labour includes electrician, steel work, engine fitter, spray painting, gas and a
                                      