Gillaroo

Home
Plans and crew
The Build
2003

Design
Model
Workshop & Table
Infusion
2004
Assembling hulls
2005
Hull Bulkheads
Bridgedeck Floor
Superstructure
2006
Completing Shell
Interior
2007
Painting
Interior
Exterior
2008
Completion
Rig
Summary
Time and Materials
Links and Suppliers

The Launch
2008
First time
Relaunch

Cruising
2008

Ireland
N.Spain
Portugal & Tarifa
Canaries

Cruising
2009

St Vincent & Grenadines
Trinidad & Tobago
Dutch Antilles
San Blas Islands (Panama)
San Blas canoes
Panama
Panama Canal
Panama - Perlas Islands
Galapagos
Galapagos
Marquesas
Marquesas
Tuomotos
Societies
Societies
Cooks
Cooks
Niue
Tonga
Tonga
New Zealand


Two hulls and a years work completed.

Assembling the hulls
Having made the four main hull panels the next stage is form them into the two hulls. The panels are grooved lengthways and dart cuts made along the keel line so that they will bend to the right shape. I did most of this work on my own and had to rig up all sorts of pulley systems to flip the panels over and move them around the workshop - a 150kg, 12m panel can be an unwieldy.

A pair of the panels are set up on edge face to face, keel line to the top. A metal T bar (the T bar is two lengths of 20mm square section steel with ties in between them - 25mm would have been better as it would have overlapped the top edge of the fibreglass panels better) is set along the keel line and held into place with cable ties. The bottom of the panels are then spread out to the appropriate hull width, making an A shape. The T bar is pulled down with ratchet ties bringing the hull into shape. The dart cuts make a number of tongues in the panel, to get these to line up smoothly some battens were screwed down to the hull.
This job took two of us about a week to get everything into shape. We had particular problems at the bow and stern where the some of the panels simply would not bend in exactly the same way - I think the likely cause of this is some resin flooding when I was having problems with the infusion process. The result is that my hulls are not perfectly symmetrical however the differences are cosmetic rather than significant.

Next the hull is glassed with CSM from the inside to hold it to shape, the T bar removed, and the outside glassed. We put an extra layer of kevlar along the keel line for extra strength. The bow at this stage is an A shape. I finished off by filling in with a sheet of foam and glassing over. Then building on a bow shape in foam, shaping as desired, and glassing over and finishing in kevlar. The result is an expendable bow section in case of serious collision.

Fairing and sanding came next, it took about 8 man weeks to fair the two hulls. I started off using resin/microballoons but later found an excellent fairing compound, Poly-Fair, which cured in minutes and was easier to sand. The pictures show some lines down the side of the hulls, this was from the joins in my table which weren't perfect however it only took a few hours to clean up each panel. The areas that took most time were around the tongues along the keel line which were not just quite level, the bow which needed shaping and the line along the hull where more glass had been added after shaping.